No. Period Project Name Employer
27 2004.08~2005.12 Electric Work of Hyundai Oil Bank Clean Fuel Project Hyundai Oil Bank/Hyundai E&C
26 2004.01~2005.06 Electric Work for "D" District of KwangYang LNG Terminal POSCO/Daelim Industrials
25 2004.01~2005.10 Temp. Controller Installation Work of 3AA Reactor LG Chemicals
24 2003.10~2005.06 Electric Work for "B" District of KwangYang LNG Terminal POSCO/Daelim Industrials
23 2003.08~2003.11 Electric Work of LG Chemical 3AA D/B Project LG Chemicals/GS E&C
22 2003.05~2003.12 Electric Work of SM Revamping Project LG Chemicals/GS E&C
21 2002.12~2002.12 Elecric Work for Dry Rotary Panel Exchange Project LG Chemicals
20 2002.12~2002.12 Instrument Work for ABS1 BL-6684 Capa Up Project LG Chemicals
19 2002.12~2002.12 Instrument Work for PS2 Pneumatic Capa Up Project LG Chemicals
18 2002.10~2003.08 Electric Work of The 3rd Air Separation Plant Honam Petrochemical/Samsung Eng.
17 2002.10~2003.04 Instrument Work of LG MMA YM-2 WWT GS E&C
16 2002.08~2003.12 Local Push Button Installation Work LG Chemicals
15 2002.05~2002.08 Fan Facility Work of Phosphate Rock Storage Namhae Chemical
14 2002.05~0203.07 E&I Work of BASF TDI Incinerator Korea BASF/Daelim Industrials
13 2002.02~0202.03 Protection Relay Installation Korea Dow Chemical